Planning Board schedules Troutbeck public hearing and hears site plan change for Silo Ridge

Troutbeck's sign along the side of Route 343 in the town of Amenia.
Photo by John Coston

Troutbeck's sign along the side of Route 343 in the town of Amenia.
AMENIA — Following a report on the plans for Phase 8 of the adaptive reuse plan submitted by Troutbeck, the Planning Board at its meeting on Wednesday, Oct. 23, voted unanimously to schedule a public hearing to be held on Wednesday, Dec. 11.
Reviewing the Troutbeck plan, Engineer Rich Rennia of Rennia Engineering of Dover Plains explained that Phase 8 would see “a small rearrangement of components.” An indoor pool to be enclosed within a pole barn will be connected with the wellness area. A small bathhouse containing rest rooms is also planned.
A net reduction in impact will result from the rearrangement, Rennia said, including reduction in wastewater generation by 240 gallons and lowered water demands.
“There is no increase to the overall project,” Rennia said, although minimal lighting will be added for pedestrian safety.
Planning Board engineer John Andrews indicated, although a health department approval is needed, he had reviewed the overall plans and found that the application is ready for public hearing. Planning Board attorney Paul Van Cott agreed, clearing the way for the board to schedule the December public hearing.
Citing a change in demographics since the existing Silo Ridge master plan was approved by the town in 2020, representatives of Silo Ridge reported to the Planning Board indicating an interest in changing two planned three-story town house structures into three-story condominium buildings to be designated on the plans as Condos D and E.
The existing approved master plan shows 245 units. No new units would result from the change.
Engineer Andrews indicated that the townhouses totaling ten units divided evenly between two buildings would have had fee-simple ownership. The change would bring condominium ownership structure.
Under fee-simple, the townhouse owner would own both the land and the building on the land. On the other hand, a condo owner owns only the condo, while the land belongs to a condo association in which the owner is considered a shareholder.
“Administratively, there are a lot of steps needed,” Andrews said, adding that although the project has changed, he felt the changes were insignificant. He noted that the Silo Ridge Design Review Committee will need to sign off on the proposed change from townhouse to condo.
To Planning Board member Ken Topolsky’s inquiry into progress on providing the board with a Silo Ridge organizational chart, O’Leary assured the board that the chart is being worked on, along with an updated progress report on the status of construction of the Silo Ridge development as a whole.
Members of the Planning Board praised the Silo Ridge Masters Show Jumping Competition held in early October at Keane Stud on Depot Hill Road, noting that the world’s top riders were attracted to compete in the four-day event. The benefit to the town of Amenia was measurable.
Keane Stud owner Juan Torres told the Planning Board that he is working on design of a new site plan for the Depot Hill area acreage to be submitted for the board’s consideration before the end of this year.
“We believe that our goals are more aligned with the community,” Torres said, adding that the aim is to protect the woods, land, habitats and natural amenities, goals outlined in the town’s Comprehensive Plan of Development.
Architect Nicole Emmons, of Hart, Howerton Architects of New York City, asked the Planning Board to describe their concerns on behalf of the town when thinking of Keane Stud Farm’s future.
Reading directly from the town’s Comprehensive Plan of Development, planning board member Topolsky said that the document guides the board’s vision.
“This is the voice of Amenia,” Topolsky said, noting that the plan emphasizes repeatedly that Depot Hill is one of the town’s most scenic features. He stressed the importance of protecting the viewshed.
Planning Board chairman Robert Boyles, who also serves the Wassaic Fire Company as Captain, mentioned a need for fire protection ponds as water sources, as well as voicing concern about runoff drainage toward properties located downhill from Depot Hill.
Board member James Vitiello said it would be important for the planners to arrive at a proposal that would be visually appealing.
“We have to turn to you, as a designer, to design something that doesn’t just maximize the dollar value but to find something the town can be comfortable with,” Vitiello advised.
“Our goal is to work together,” Torres said.
George Janes, the town’s visual resources consultant, said that he was in agreement with the concept of 10-acre agricultural parcels as initially described.
“What makes the Depot Hill viewshed special is its present agricultural landscape,” Janes said.
“You’re subdividing, not developing,” he pointed out to Torres.
Discussion included the role of deed restrictions in limiting the eventual development of each 10-acre piece by those who will purchase them.
Board member John Stefanopoulos indicated the possibility that parcels can be developed in ways that will blend with the scenery and add value, constrained by deed restrictions written correctly.
“The Planning Board is not going to design it for you,” Janes told Torres and Emmons, suggesting that they find guidance within the town’s comprehensive plan.
Before the Planning Board adjourned, Wassaic resident Sharon Kroeger provided notice of a petition gathering signatures intended to preserve and protect the Delavergne Hill viewshed that includes Depot Hill.
North East Supervisor Chris Kennan, center left, presents outgoing Town Board member Ralph Fedele with a commemorative gift in recognition of his 12 years of service. Fedele, who retired in December 2025, received the gift during the Jan. 2 annual organizational meeting.
MILLERTON — The North East Town Board convened for its annual organizational meeting on Friday, Jan. 2, where trustees affirmed priorities and set the tone for the year ahead.
“I’m really proud of the town hall that we have,” said Supervisor Chris Kennan. “I think we have a great group of people who work together well, and it’s a collegial place to be.”
Kennan’s three major priorities for the coming year include renovating and occupying the new Town Hall, continuing work on the town’s long-anticipated zoning revisions, and advancing plans for a wastewater and sewer system in Millerton.
Work on the new Town Hall is expected to begin in earnest this year, Kennan said. He also expressed cautious optimism about progress on a sewer system, citing a recent meeting with U.S. Rep. Pat Ryan, D-18, and noting that a previously stalled federal grant will move forward. The funding, he said, would cover a significant portion of the project’s engineering costs.
Additional grant applications are in progress, and the town and village continue to evaluate long-term options. Kennan described the completion of the project as “transformative” for Millerton, even if the impact would unfold gradually over time.
With a public hearing on the new commercial zoning draft scheduled for Thursday, Jan. 8, at 7:05 p.m. at Town Hall, Kennan acknowledged the complexity and urgency of the effort. The town’s code has not been significantly updated since 1977.
“I’m really proud of the work that the town has done to get to where we are at the moment,” Kennan said, adding that he is looking forward to the second phase of the zoning rewrite, which will look at residential zoning after the commercial district is finalized.
The board also reviewed and approved the 2026 rules of procedure for Town Board meetings, including a discussion about public comment. Although public comment is not required by law, North East welcomes it. Under the updated rules, individual speaking time will be reduced from five to three minutes, a change that Kennan says aligns with practices in surrounding towns.
During the meeting, the Board officially welcomed newly elected Councilwoman Rachele Grieco Cole and said a final farewell to outgoing board member Ralph Fedele, who retired after 12 years of service. Kennan presented Fedele with a commemorative gift in recognition of his years of service. Fedele thanked the board, noting how much the town has changed during his tenure.
“A lot has changed in 12 years, and I’m going to miss all of you,” Fedele said.
Newly re-elected Councilman Chris Mayville was appointed deputy supervisor. Mayville and Councilwoman Meg Winkler were also designated as emergency interim successors.
Much of the remainder of the meeting focused on routine appointments and reappointments. The board reappointed Daniel Sternberg to the Planning Board following the expiration of his term on Dec. 31, 2025, and reappointed Dale Culver as Planning Board Chair through Dec. 31, 2026. Bob Stevens was reappointed to continue serving as the highway superintendent.
With a vacancy on the Zoning Board of Appeals, the board reviewed an application from Henry Smedley and voted to appoint him to the board. Edie Greenwood will continue to serve as chair through Dec. 31, 2026.
The board formally designated Kenneth McLaughlin, the town’s building inspector, as zoning enforcement officer, noting that while the position is referenced in the town code, it had not been formally assigned in the past.
The board also approved standard organizational items, including regular meeting times and designated depositories, official newspapers, and engineering services, to name a few. The group also discussed ongoing training opportunities for new and returning officers offered by the New York State Association of Towns.
Farmland vista where one of the proposed solar arrays for Hecate Energy's proposed Shepherd's Run solar energy array on Route 23 in Craryville, New York.
COPAKE – The past year marked another herky-jerky dance on the community solar front for this otherwise quiet hamlet.
As 2025 rolled along, the battle between Hecate Energy LLC and residents opposed to its proposed 42-megawatt Shepherd’s Run solar farm entered its eighth year.
In February, New York State officials dismissed the company’s application, and the process of review continued through the rest of the year. Officials in Albany eventually issued two additional notices of incompleteness.
Meanwhile, state legislators also weighed in on the project. State Sen. Michelle Hinchey, D-41, and State Assemblywoman Didi Barrett, D-106, both expressed concerns about the project in letters to state officials and to Gov. Kathy Hochul. Hudson Mayor Kamal Johnson wrote about concerns the city’s Common Council cited in October 2024 about the safety of Hudson’s water supply.
The project has been controversial since it initially was discussed in 2017 — planned as a 60-megawatt solar farm to be located on farmland near the intersection of Routes 23 and 7. In January 2024, the project had to be downsized after the company lost control over a portion of designated land. As it now stands, Shepherd’s Run will span 700 acres with thousands of solar panels covering 225 acres.
In other developments, last summer Hecate found itself in Delaware Chancery Court as a creditor sought a restraining order against the Chicago-based developer, owner and operator of renewable power projects. A Hecate lender claimed: “Hecate Holdings is woefully insolvent, strapped for cash, and drastically over leveraged,” a motion stated. Then, soon thereafter, a second creditor filed a similar motion in the same court claiming Hecate was in default in its loan agreements.
By the middle of the next month, in September, state officials accepted the company’s Shepherd’s Run application as “complete” and within a requisite 60-day period issued a draft permit for the project. That was in mid-November.
Next up will be public hearings. Two will be virtual airings available on Tuesday, Jan. 27, at 2 p.m. and 6 p.m. Four in-person hearings are scheduled for 2 p.m. and 6 p.m. on Wednesday, Jan. 21, 2026, and Thursday, Jan. 22, 2026, at Town Hall in Copake.
On Jan. 10, from noon to 2 p.m. at the Copake Memorial Park Building some residents have organized a community meeting in preparation of the public hearings. Organized by Sensible Solar for Rural New York and the Arcadian Alliance, the meeting will feature talks and videos “to hear experts on how Shepherd’s Run will negatively impact Copake.” Speakers include Town Supervisor Richard Wolf, William Murphy, a retired battalion chief from the Fire Department of New York and Lindsay Brecht of Copake Lake Realty.
The Millerton Square plaza is still empty on Friday, Jan. 2, a little over eight months since the Town of North East Planning Board approved a site plan for major renovations to the grocery store in April.
MILLERTON – At a glance, Millerton’s year was marked by striking contrasts. Moments of division were set against moments of community building. Major municipal milestones were followed by delays and missed deadlines. And years-long efforts to prepare for the future unfolded alongside planning efforts to celebrate the past.
A Feb. 3 fire shaped what would become a year of rebuilding and resilience for the Village of Millerton. The early-morning blaze destroyed the highway and water department building, incinerating the village’s police vehicles, snow-removal equipment and everything inside the building.
What followed was an impressive effort to replace critical infrastructure, secure emergency funding, file and manage insurance claims and reimagine long-term plans for the site. The loss ignited nearly a year of logistical challenges, but also revealed a supportive community of workers, volunteers and neighbors. Demolition of the building began on Oct. 27, and efforts to build two new structures will begin early this year, although an official construction timeline has not been released by the village.

One of the biggest questions on residents’ minds this year was the long-awaited return of a full-scale grocery store to Millerton. Early optimism followed the 2024 sale of the Millerton Square Plaza to Kim and Chris Choe, veteran grocers who own the Sharon Farm Market. After the Town of North East Planning Board approved their site plan earlier this spring, many hoped the new “Town Gourmet Market” would open in 2025. The owners even floated an October target.
But as fall came and went, the plaza’s parking lot remained cluttered with debris, and visible disrepair raised new questions about timing. During a recent visit to the couple’s newly opened New Haven store, Market 360, co-owner Kim Choe said extensive interior renovations have delayed progress and that no updated timeline is available. Still, Choe emphasized that the project is moving forward.
In May, a group of residents and neighbors concerned about national immigration enforcement urged the Village Board to adopt a local law prohibiting Millerton police from assisting U.S. Immigration and Customs Enforcement (ICE) without a judicial warrant. Their request was heard at a May 21 board meeting, but momentum surged ahead of a July 29 follow-up meeting that drew nearly triple the crowd. The discussion revealed a deeply divided community. Ultimately, trustees declined to pursue the proposal, and Millerton Police said they would fully cooperate with federal authorities, including ICE, even without a judicial warrant, while noting that the department does not collect immigration status information.
In spite of that decision, local advocates have continued to organize independently. Residents have sought “Know Your Rights” training and rapid-response preparation through regional organizations such as the Columbia County Sanctuary Movement and Vecinos Seguros 2, building informal networks to support neighbors who may be vulnerable. While the village chose not to adopt the new policy, these community-led efforts reflect a broader regional movement to ensure residents understand their rights and have support in an increasingly uncertain enforcement landscape.

Millerton’s long-awaited pool at Eddie Collins Park saw both disappointment and progress this year. In July, Mayor Jenn Najdek announced that construction – originally scheduled to begin in spring 2025 – had been pushed to 2026 due to ongoing wetlands and septic-related reviews by county and state agencies. Residents and officials alike were disappointed that the pool will not be ready for the village’s upcoming 175th celebration in July. Trustees chose to delay construction until after the event, ensuring residents have a place to gather.
Even so, planning continues. Architects from LaBella Associates presented updated designs in December 2025, and trustees finalized several key decisions, including opting against a heated pool because of cost and choosing a fully equipped commercial kitchen for the pool house. With design details now refined and ready for county review, village officials say the project remains very much alive – just on a longer timeline than originally planned.
Zoning, often an overlooked topic, became one of the year’s most contentious issues, as the Town of North East moved toward a rewrite of its commercial zoning code for the first time since the 1970s. After four years of work by the volunteer Zoning Review Committee (ZRC) and nearly a year of Town Board review, officials released a 181-page draft in November outlining major updates intended to modernize the code. Officials stated that additional goals were to encourage new housing options, streamline approvals and support local business growth. A public hearing is set for Jan. 8, where residents will have an opportunity to weigh in.
In recent weeks, however, a group called “Save Millerton” has challenged the process, publishing information that alleges poor transparency, overly dense housing allowances and lax zoning enforcement. Town officials reject those claims, calling them misleading and emphasizing that the rewrite reflects years of public meetings, professional planning input and the goals laid out in the 2019 Comprehensive Plan.
Supervisor Chris Kennan said revisions may still follow the Jan. 8 hearing and stressed that the updated code is designed to encourage much-needed housing and welcome new and existing business development.
Even amid delay and division, Millerton continued to show up for one another. The community turned out in numbers for major events like the Oblong Books 50th Birthday Celebration, the Millerton News Street Fair and the Memorial Day Parade. And while zoning will continue to take center stage and shape Millerton’s future, planning is in full swing to honor its past with the 175th committee working alongside business owners and residents to create a birthday bash in July.
Road crews began construction in August on a new sidewalk along Route 44 connecting Amenia’s town center to Beekman Park, a project scheduled for completion in spring 2026.
The past year in Amenia was marked by steady progress on infrastructure, preservation and community projects designed to improve daily life and position the town for future growth.
In March, the Town Board selected a contractor to extend the sidewalk along Route 44 between Broadway and Beekman Park, with construction beginning in August. When completed this spring, the project will provide a safer pedestrian connection between the town center and the park.
Work also advanced on plans for a new town garage and salt shed. Town crews completed site preparation throughout the year, handling initial land clearing and grading in advance of construction, which is scheduled to begin this spring.
Community groups played a role in enhancing public spaces as well. In early May, members of the Amenia Garden Club planted a native pollinator garden at the Amenia Free Library. Now established, the garden continues to attract bees, insects and birds native to the region.
New businesses added energy to the town in 2025. Isabela, Amenia’s newest restaurant, opened in late March and quickly built a loyal following, drawing steady local interest. In July, the Silo Bakery also opened in Amenia, offering an array of pastries, breads and pies and becoming another popular destination.
Preservation efforts also moved forward during the year. In late May, donations from the Amenia Historical Society and local residents supported restoration work on the town’s 1937 Sanford fire truck. Once complete, the town’s first fire engine is expected to return to public view, including appearances in local parades.
A long-anticipated preservation milestone was marked on July 3, when the town officially accepted the donation of the historic Wassaic Charcoal Kilns. The ceremony formalized the transfer of the two restored 19th-century stone kilns to the town on the eve of Independence Day celebrations.

Community events drew visitors throughout the year. Despite clouds and intermittent rain, classic cars lined Wassaic’s Main Street in late May for a car show organized by Fenders and Flowers. In mid-October, months of planning culminated in the first annual Amenia Harvest Festival, which brought together vendors, residents and visitors.
Equestrian events also expanded in 2025. The Silo Ridge Masters returned to Keane Stud with an additional weekend of show-jumping competition. Riders were drawn to Amenia again in early October for a three-star competition, followed the next week by a new five-star event under the Highlands Cup banner. The expanded competition included two nights of concerts and a car competition.
Voters weighed in during the November election, continuing the town’s support for Democratic candidates. Rosanna Hamm won the supervisor’s race, defeating Republican Terrence McCauley by a margin of 686 to 402. Democrats also strengthened their presence on the Town Board, with Walter Dietrich winning one of two full-term seats and Vicki Doyle securing the remaining year of an unexpired term. Republican Nicole Ahearn won the second full-term seat.
Amenia voters also narrowly chose to retain the town’s ban on retail cannabis sales, approving the measure by a vote of 560 to 515.
Looking ahead, the coming year is expected to bring the completion of the Route 44 sidewalk project and construction of the new town garage and salt shed, along with continued progress on repairs to the Water District’s facilities, including new well heads and pumping station.