Board scrutinizes Pine Plains solar project

PINE PLAINS — More than 30 residents attended a Planning Board public workshop on Saturday, March 11, to learn about the status of a proposed community solar project proposed near Pulvers Corners that is under review.

As the meeting began in the Community Room of the Pine Plains Free Library, 7775 S. Main St., residents were presented with a summation of issues that have been identified by the Board.

Planning Board Chairman  Michael Stabile began with a nuts-and-bolts explanation of the role of the board in evaluating the application by Carson Power of New York City, and introduced Frank Fish of BFJ Planning of New York, a planning consulting firm.

Fish reviewed the town’s solar law as well as the Planning Board’s role and responsibilities in considering the application to install a Tier-3 solar plant, which, under town law adopted in 2022, is considered a large-scale solar installation. The project would require a special permit and site-plan approval if it advances.

The three big study areas of the Planning Board, Fish said, are impact on habitat, visual impact of the project and evaluating the project’s consistency with community character.

“Now we’re approaching the end of the beginning of the process,” said Stabile, noting that the Board has held public hearings and workshops on Carson Power’s application and considered some environmental questions.

Stabile talked through a list of issues that have surfaced from public comments and from the Board, at times providing the Board’s perspective on the relevance of concerns raised.

At the outset, Stabile announced that — time permitting at the end of the workshop — anyone who wished to speak would be given the opportunity.

The list of issues included concerns about whether there were wetlands on the proposed site, the impact of cutting trees, threats to wildlife, runoff concerns and issues related to the use of herbicides. There also were issues raised about the impact on property values of nearby residents, including the visual impact of a 171-acre solar farm with 24,000 panels on agricultural and forested land, plus questions about traffic and safety.

“There are still some outstanding questions,” Stabile said, reiterating that the Board is evaluating all the things that have been said by Carson Power as well as all comments from the public. “This meeting is a review of the Planning Board’s work and the hearings that have been held to date.”

Ten residents who live near the project, to be located off Bean River Road, have organized their opposition to the project by hiring Grant and Lyons LLP of Rhinebeck, an environmental land use, zoning and real estate law firm.

John Lyons of Grant and Lyons submitted new comments to the Board prior to Saturday’s workshop that were based on expert reviews. The expert group includes: Erik Kaviat, co-founder of Hudsonia Ltd; George Janes, a planner; and Nan Stolzenburg, a community and environmental planner.

“We don’t agree with the sort of semi-conclusions that have been reached so far on some things,” Lyons told the Board Saturday. “We have some real questions about visual assessment. Visual impact is one of the biggest impacts posed by this project.”

Lyons also said that it may seem obvious that the project is consistent with the town’s Comprehensive Plan, but it’s a much more complicated question.

All three experts, who did not attend Saturday’s workshop,  concluded in their reports that the project deserved further study.

Stolzenburg wrote:  “It is my opinion that the Carson Solar proposed project is not consistent with the Town’s Comprehensive Plan, nor with community character and that there are many areas where there are potentially significant adverse environmental impacts to community character.”

Kaviat was critical of the level of detail in the application. “The proposal lacks important detail as to site preparation, construction, and operation, especially with regard to soil management and large trees, and including agricultural co-location and pollinator plantings, to ensure that the project’s harm to biodiversity is minimized and mitigated.”

Kaviat recommends taking a hard look at the potential impacts on the bog turtles, bats, large trees, forests, downslope and offsite waters and wetlands, among others.

Jaynes concluded that “this project may cause a significant adverse impact on visual resources. The materials that the applicant produced simply do not demonstrate the potential for visual impacts.”

Lyons is advocating for a “positive declaration” by the Planning Board, which would  require Carson Power to prepare an environmental impact statement that studies the significant adverse environmental impact and proposes mitigation.

A few other residents spoke to the board Saturday after the workshop ended, including Allison Galliher, a resident of Skunks Misery Road, who said her family is involved in the community — in the schools, by volunteering, getting involved in the Little League. “We’re trying to make a positive impact to our community, where we’re living,” she said.

“They (Carson Power) don’t have a long-term interest here,” she said to applause from those present.

Allison Galliher of Pine Plains commented on Saturday, March 11, that Carson Power doesn’t have a long-term interest in the town. Photo by John Coston

Provided by Pine Plains Planning Board

Provided by Pine Plains Planning Board

Latest News

Check-in at Bulk Trash Day
Photo by John Coston

Mickey Stringer of of North East, left, checks in with Chris Virtuoso, volunteering on Saturday, May 12 at the Old Town Garage on South Center Street as a Climate Smart Task Force member. Stringer’s loaded pickup was part of a long line of vehicles along South Center as residents used the opportunity to dispose of air conditioners, mattresses, lumber, and other bulk items. Town Supervisor Christopher Kennan said he didn’t recall seeing such a long line of vehicles in past years.

Millbrook airs school budget, propositions ahead of  May 20 vote

Elm Drive Elementary School in Millbrook.

Archive photo

MILLBROOK — Preparing for the village-wide vote on the proposed 2025-26 school budget scheduled for Tuesday, May 20, the Millbrook Central School District held a public hearing on Tuesday, May 6, to review the budget and hear residents’ comments.

The CSD proposed 2025-26 budget to be voted upon as Proposition 1, showed total expenditures of $35,649,651, an increase of $1,074,576 (3.11%) over the current year.

Keep ReadingShow less
Millerton Zoning Board of Appeals hears new variance request for 7-9 Main Street

Ray Nelson, Earthwise Architecture, requested two variances for 7-9 Main St., one to allow a 9-unit floorplan and another to waive the parking requirements for the building, at a public hearing held by the village Zoning Board of Appeals on Tuesday, May 6.

Photo by John Coston

MILLERTON — Ray Nelson of Millerton presented two possible updated floorplans for the apartment building at 7-9 Main St. to the Zoning Board of Appeals at a public hearing on Tuesday, May 6.

Nelson, on behalf of the building’s owner, is seeking two variances for the property: one allowing a density increase and another waiving the parking requirements for the property.

Keep ReadingShow less
Irondale Schoolhouse to ring bell on opening day May 24

Ralph Fedele with Mary Leitch, 103, who attended the one-room Irondale Schoolhouse until it closed and she moved on to Millerton High School.

Photo provided

MILLERTON — The Irondale Schoolhouse will celebrate its opening day on Saturday, May 24, when it will ring in its eleventh summer season with the old school bell.

Lemonade and cookies will be provided for visitors. A history exhibit is on display inside the schoolhouse and there will be a formal unveiling of a plaque commemorating membership in the Country Schools of America, a nonprofit dedicated to preserving the memory of country schools.

Keep ReadingShow less