Webutuck’s $12.6 million project to begin this summer

Webutuck’s $12.6 million project to begin this summer
Courtesy Webutuck Central School District

AMENIA — The final contractor bids for the North East Webutuck Central School District capital improvement project were accepted at the WCSD Board of Education’s Monday, Feb. 12 meeting. Work is slated to begin this summer.

The board first proposed the Webutuck CSD capital improvement project in December 2022. Once the project was voted on and approved in May 2023, the board began soliciting contract bids.

The work will be done with no additional tax impact on residents because a capital improvement debt incurred 20 years ago will be paid off at the same time the new debt is added, and dollar for dollar, the amount is almost the same.

In December 2022, the board named three reasons for the proposed projects, saying they were need-based, necessary for the health and safety of the students and staff, and that they focused on critical infrastructure needs.

The improvements that the contractors will begin this summer include facilities updates: on-site parking, sidewalks and roofs must all be replaced due to aging and normal wear and tear. Some elements of the sanitary system have also aged out.

Taking care of the facilities means less chance of unexpected problems such as burst pipes — in January 2022, a burst pipe flooded the school’s auditorium with six inches of water — data loss, and missed school days, explained Webutuck CSD Superintendent Raymond Castellani.

In the Webutuck Elementary School (WEB), air conditioning will be installed in some of the classrooms used for summer programs.

An age-appropriate playground at Eugene Brooks Intermediate School (EBIS) for fourth through eighth grade students, who currently have no playground of their own, will also be built.

The Capital Improvement Project will also prioritize an emergency generator to provide protection of the security system, technology and mechanical operations throughout the school district.

At all three schools, the roofs will be replaced and unit ventilation systems that enable fresh air exchange will be installed.

At the intermediate and high schools, there will be milling/repaving of the parking lots and sidewalks as well as installation of a standby generator to protect technology in case of loss of power.

Castellani shared the winning bids after the Feb. 12 meeting. General construction went to Ferrari and Sons, Poughkeepsie, at $84,000; mechanical construction to Tancillott at $990,000; and electric construction to Foremost Electric at $514,900.

Sitework construction went to Land V Scape, Carmel, at $1.54 million, and state mechanicals for the elementary school went to TRANE at $540,918.

Roofing went to Garland Roofing at $5,918,000 million; and Field Turf USA will resurface the multicourt and tennis court for $108,674.

The work will most likely start as soon as school gets out, and Castellani hopes that it will largely be completed by the time school begins again in September.

The original capital plan from December 2022 can be found on the district website at webutuckcsd.org

Latest News

North East Town Board approves truck loan, hears school funding concerns

North East Town Hall on Maple Avenue in Millerton.

Photo by Nathan Miller

MILLERTON — North East Town Board members approved a $168,000 loan from the Bank of Millbrook to purchase a new truck for the town’s Highway Department at their regular meeting Thursday, Dec. 11.

The meeting marked the board’s final session of the year.

Keep ReadingShow less
Village of Millerton sets stage for zoning overhaul, aims for transparency

Millerton Village Hall, where the Zoning Board of Appeals has begun laying the groundwork for a zoning overhaul aimed at modernizing the village’s code.

Nathan Miller

MILLERTON – The village Zoning Board of Appeals (ZBA) met on Tuesday night to begin laying the groundwork for a long-anticipated update to its zoning code — a process officials say is necessary to replace regulations they repeatedly describe as “outdated.” The discussion comes as the Town of North East faces public scrutiny over its November release of a years-long zoning rewrite of its commercial district.

To better understand the rewrite process — and avoid replicating challenges the town has encountered — ZBA Chair Kelly Kilmer invited two members of the North East Zoning Review Committee (ZRC), Edie Greenwood and David Sherman, to share insight.

Keep ReadingShow less
Snowstorm forces Millerton, Amenia and Pine Plains to reschedule board meetings
Amenia Town Hall
By Nathan Miller

Correction: The Amenia Planning Board does not have another meeting scheduled prior to the end of the year. It is currently unclear if the board will schedule another meeting to make up for the cancelled meeting on Dec. 10.

A snowstorm that dropped about an inch across northeast Dutchess County forced the cancellation of municipal board meetings in the Village of Millerton, Amenia and Pine Plains on Wednesday, Dec. 10.

Keep ReadingShow less
Our visit to Hancock Shaker Village

The Stone Round Barn at Hancock Shaker Village.

Jennifer Almquist

My husband Tom, our friend Jim Jasper and I spent the day at Hancock Shaker Village in Pittsfield, Massachusetts. A cold, blustery wind shook the limbs of an ancient apple tree still clinging to golden fruit. Spitting sleet drove us inside for warmth, and the lusty smells of manure from the goats, sheep, pigs and chickens in the Stone Round Barn filled our senses. We traveled back in time down sparse hallways lined with endless peg racks. The winter light was slightly crooked through the panes of old glass. The quiet life of the Shakers is preserved simply.

Shakers referred to their farm as the City of Peace.Jennifer Almquist

Keep ReadingShow less