State denies Shepherd’s Run 60MW solar project
Farmland vista where the proposed 880-acre, 60 megawatt Shepherd’s Run Solar Farm is planned along Route 23 at the entryway to the rural hamlet of Copake. Opponents say the project, big enough to power the equivalent of 15,000 homes annually, would detract from the scenic farmland community.
Photo by John Coston

State denies Shepherd’s Run 60MW solar project

COPAKE — The state approved the Town of Copake’s motion to dismiss last week, ending Hecate Energy LLC’s bid to build a 60-megawatt solar farm, known as Shepherd’s Run, at the at the intersection of Routes 23 and 7.

The executive director of state Office of Renewable Energy Siting (ORES), Houtan Moeveni, issued a decision Tuesday, Feb. 6, following a month of legal filings that were triggered after it became known that Hecate had lost control of a parcel of land that had been part of the proposal.

“The Town’s motion to dismiss the application is granted, and the application is denied without prejudice to Hecate’s submission of a new application for a modified project,” Moeveni wrote in his decision.

“The ball’s back in Hecate’s court,” said Richard Wolf, supervisor of the Town of Copake.

Approximately 75 residents attended a town board meeting on Thursday, Feb. 8 to hear about the state’s decision. Wolf said many urged the town to stay the course in seeking the best possible solution for renewable energy in Copake.

“This is not over,” he told residents.

Hecate Energy could not be reached for comment.

Last August, ORES had issued a notice of “complete application” and the project was on track until it became apparent that the company had lost access to the 60-acre parcel.

That parcel, initially included in the project, would have hosted up to 20% of the farm’s solar panels, and provide for a “laydown area” and road access to adjacent parcels. The project footprint spans 880 acres with a solar array covering about 220 acres.

The Town of Copake filed with the ORES office seeking dismissal of Hecate’s application based on the new information and claiming that a redesign of the project is required.

Hecate Energy responded in a filing in late January that the company planned to submit a revised application, and would reduce the generating capacity of Shepherd’s Run from 60MW to 42MW as a result of the loss of the 60-acre parcel.

In that filing, Diane Sullivan, a senior vice president of environmental and permitting at Hecate Energy, said that the company planned to submit a revised plan within 60 days. Hecate also argued that Moaveni had leeway to “proceed in ways not addressed by the ORES staff response.” The agency’s staff, citing Executive Law 94-c, disagreed that there was a way to proceed, as Hecate said in its filing “without requiring an unnecessary, time consuming and potentially complex full withdrawal and resubmission of an entirely new application.”

Moeveni’s decision noted the law’s “efficient, equitable, and predictable process for the expeditious review of major renewable energy facilities […] without compromising environmental protection and community participation.

“Departing from that process to address Hecate’s own mistake is unsupportable as a matter of law, and would adversely impact the integrity of the Executive Law 94-c.”

Sensible Solar for Rural New York, a group of citizens opposed to the project, concurred with the town’s motion to dismiss Hecate’s application.

Latest News

Amenia approves sidewalk projectalong Route 44
Amenia Town Hall
Photo by John Coston

AMENIA — Pedestrians will soon be able to walk safely between Broadway and Beekman Park, now that a construction contract has been awarded.

The planning process continued for many months, culminating in an invitation to bid. The Town Board voted unanimously at its regular meeting on Thursday, March 20, to select the lowest bidder, clearing the way for work to begin.

Keep ReadingShow less
Science confirms: It was a cold winter

Spring has officially arrived with freezing night time temperatures forecast through the first week of April.

Photo by Krista A. Briggs

Victoria Kelly, Cary Institute Environmental Monitoring Program Manager and Senior Ecologist, prepared this report.

MILLBROOK — Since 1988 the weather station at the Cary Institute of Ecosystem Studies in the Town of Washington has been keeping track of our local weather — precipitation, temperature, wind, air quality, etc.

Keep ReadingShow less
North East Fire District focuses on budget, spending

The North East Fire house on the south side of Century Boulevard.

Photo by Krista A. Briggs

MILLERTON — The commissioners of the North East Fire District recently held their monthly meeting at the firehouse to discuss their current needs and general business.

Discussion centered around the current work on the 2025 budget and proposed expenditures, which ranged from upgrading their heating/cooling system to the possibility of replacing car no. 3.

Keep ReadingShow less
North East okays Village use of old highway garage

Town supervisor Chris Kennan hands memorandum of understanding documents to Millerton Mayor Jenn Najdek for her signature at the town board’s special meeting on March 21. Town councilperson Chris Mayville, left, and deputy supervisor Lana Morrison, right, in foreground.

Photo by Krista A. Briggs

MILLERTON – The Village’s need for space in the wake of the fire that gutted the Water and Highway building last month was addressed at a special meeting of the town board on Friday, March 21.

By a unanimous vote, the board approved a resolution to grant the Village usage of the Town’s old highway garage on South Center Street.

Keep ReadingShow less