Shepherd’s Run project still facing headwinds

COPAKE — The Shepherd’s Run Solar Farm project faces further review by state officials in Albany following new filings last week from the town of Copake, residents for and against the project and Hecate Energy LLC.

The town is seeking dismissal of the company’s application to build on farmland along routes 23 and 7 based on several developments, principal among them that the company has lost control of land it originally said it needed for a 60-megawatt facility.

The state Office of Renewable Energy Siting (ORES) staff last month stated:

“Depending on the scope of the changes required, the Office (staff) also observed that the Office could deny a final siting permit if significant changes to the design of a proposed facility were required.”

If revisions to an application were required, ORES determined, such changes could be made: (a) by an applicant by withdrawing and resubmitting the application; or (b) by ORES by reflecting any changes in the final siting permit.

New York’s lofty solar goals

New York state seeks to achieve 70% renewable electricity by 2030, a goal established by the Climate Leadership and Community Protection Act, a landmark bill passed in 2019 by the New York Legislature. It further aspires to achieve 100% emissions-free electricity by 2040.

Gov. Kathy Hochul, in her State of the State address last month, announced additional clean energy initiatives, including a proposed Renewable Action Through Project Interconnection and Deployment (RAPID) Act. Chief among provisions of the RAPID Act is a transfer of ORES operations to the state Department of Public Service, which manages transmission siting and planning.

The fight on the ground

Hecate Energy, in recent filings with ORES, argues that the agency’s executive director, Houtan Moaveni, has broad authority to take action in furtherance of the state’s renewable energy goals.

However, the ORES staff, in a response to that statement, noted that such action is “inconsistent with applicable statutory and regulatory authorities, as well as underlying policy.”

Letters filed last week with ORES by residents in the vicinity of the proposed solar farm reflect sentiments on both sides of the issue. Some cited threats to protected wetlands and impacts on summer recreation at Copake Lake as well as property values and the loss of prime farmland.

Another writer expressed concern about the impact on heritage tourism that is fed by the town’s seven historic properties.

Sensible Solar for Rural New York, a coalition of Columbia County citizens opposed to the Shepherd’s Run project, wrote to ORES, “Our response to that is: every developer, especially Hecate, which has misled everyone during this application process, should absolutely have to be held to the rules.”

Other letter writers point to the benefits of solar, and urge ORES to “objectively consider the facts around this project and issue a 94-c Permit to Hecate Energy without applying any burdensome local law or ordinance.”

Section 94-c refers to the state’s renewable energy development program that aims to carry out coordinated and timely reviews of projects by ORES.

Last week in responding to the latest filings by Hecate and the town of Copake, the ORES staff’s conclusion appeared to endorse an approach that would take into consideration Hecate’s plan to redesign the project to a 42MW capacity, with other changes to be considered based on the loss of the 60-acre land parcel.

In its conclusion, ORES staff wrote that “[Administrative Law Judge Maureen]” Leary’s ruling appears to provide for a further process that is consistent with the process contemplated by regulation.”

“Notably, the Applicant has for the first time […] provided details as to how it intends to address the loss of site control of a portion of the Facility site. Based on the Office’s review of such new material, it appears that the loss of site control of a portion of the Facility site may not be dispositive to the final merits of the Application as originally indicated. Thus, […]further review of the scope of the changes contemplated by the Applicant in the issues determination proceeding may be appropriate.”

In short: Copake’s appeal is pending, and the case is in the hands of ORES Executive Director Moaveni.

Latest News

Speed cameras gain ground in Connecticut, stall in Dutchess County

A speed enforcement camera in New York City.

Photo courtesy NYC DOT

Speed cameras remain a tough sell across northwest Connecticut — and are still absent from local roads in neighboring Dutchess County.

Town leaders across northwest Connecticut are moving cautiously on speed cameras, despite a state law passed in 2023 that allows municipalities to install them. In contrast, no towns or villages in Dutchess County currently operate local automated speed-camera programs, even as New York City has relied on the technology for years.

Keep ReadingShow less
In remembrance:
Tim Prentice and the art of making the wind visible
In remembrance: Tim Prentice and the art of making the wind visible
In remembrance: Tim Prentice and the art of making the wind visible

There are artists who make objects, and then there are artists who alter the way we move through the world. Tim Prentice belonged to the latter. The kinetic sculptor, architect and longtime Cornwall resident died in November 2025 at age 95, leaving a legacy of what he called “toys for the wind,” work that did not simply occupy space but activated it, inviting viewers to slow down, look longer and feel more deeply the invisible forces that shape daily life.

Prentice received a master’s degree from the Yale School of Art and Architecture in 1960, where he studied with German-born American artist and educator Josef Albers, taking his course once as an undergraduate and again in graduate school.In “The Air Made Visible,” a 2024 short film by the Vision & Art Project produced by the American Macular Degeneration Fund, a nonprofit organization that documents artists working with vision loss, Prentice spoke of his admiration for Albers’ discipline and his ability to strip away everything but color. He recalled thinking, “If I could do that same thing with motion, I’d have a chance of finding a new form.”

Keep ReadingShow less
Strategic partnership unites design, architecture and construction

Hyalite Builders is leading the structural rehabilitation of The Stissing Center in Pine Plains.

Provided

For homeowners overwhelmed by juggling designers, architects and contractors, a new Salisbury-based collaboration is offering a one-team approach from concept to construction. Casa Marcelo Interior Design Studio, based in Salisbury, has joined forces with Charles Matz Architect, led by Charles Matz, AIA RIBA, and Hyalite Builders, led by Matt Soleau. The alliance introduces an integrated design-build model that aims to streamline the sometimes-fragmented process of home renovation and new construction.

“The whole thing is based on integrated services,” said Marcelo, founder of Casa Marcelo. “Normally when clients come to us, they are coming to us for design. But there’s also some architecture and construction that needs to happen eventually. So, I thought, why don’t we just partner with people that we know we can work well with together?”

Keep ReadingShow less