Thank you!
Your support is sustaining the future of local news in our communities.

Millbrook School District capital project still in earliest phase

Millbrook School District capital project still in earliest phase
Elm Drive Elementary School in Millbrook.
Archive photo

MILLBROOK — Since voters approved planned construction work throughout the Central School District, the district board decided on a phased approach to the work in order to move ahead with the most pressing needs.

A statement from Elliot Garcia, Assistant Superintendent for Business and Personnel, outlined the two phases in three parts and gave a timeline for completion.

“The process is detailed and lengthy, but necessary to be certain that the work is done properly,” Garcia said, adding that the start of actual construction work is still months away.

The project is currently in the Schematic Design Phase, Garcia explained, a step when all of the project plans are drawn, including engineering, architectural design and equipment specifications. Part of this design phase is to create a detailed assessment of current conditions such as precise measuring of each window slated for replacement.

Once the detailed plan drawings are completed, they need to be submitted to the state’s Education Department for review and to make any modifications to meet state law and building codes. It will take time to complete the back-and-forth negotiation of those findings before the phased project can go out for bid, Garcia said.

As bids are received, they will be opened publicly and reviewed by district administration and then passed on to the Board of Education for awarding of contracts. Construction will begin soon after, to be scheduled by the contractors.

The overall project has been broken into three phases to allow the most pressing repair work, involving less design work, to progress more swiftly through the process, Garcia explained. An example is the work that is critically needed at the Middle School.

Design work on the two parts of Phase One is to be done first. The design of the Middle School roof replacement, HVAC replacement and Energy Performance began in June, Garcia reported. Plans for that aspect are projected to be submitted to the state Education Department in March 2026. Under that schedule, work might be expected to occur over two summers, 2027 and 2028, when school is not in session.

The other Phase One work will involve the Middle School accessibility renovations and window replacement, with work projected to occur over a nine-month period between July 2026 and May 2027.

The design of Phase Two — Elm Drive and Alden Place — would be slated to begin in June 2026 with plans submitted to the state by spring 2027 and construction projected to occur in summer 2027 aiming for completion in summer 2028.

Overall, the entire project will likely take a minimum of three years to complete, Garcia said of the timeline.

“These much-needed improvements to our buildings will help us better build our students for their futures, and we can only do so thanks to the incredible support we received from our voters,” Garcia said.

Latest News

After conquering Netflix, a local actor tackles high school

Ivan Howe, 13, performs as Peter Pan at the Sharon Playhouse in Sharon, Connecticut. Howe began his acting career on stage at the Playhouse in “Oliver!” in 2023 and has since performed on stage and even taken a supporting role in the Netflix miniseries “Eric” starring British actor Benedict Cumberbatch.

Photo Provided

MILLBROOK — Ivan Howe’s acting career might be growing faster than he is.

In 2023, the Indian Mountain School student and Millbrook native landed his first title role in Sharon Playhouse’s production of “Oliver!” Three years later, he’s about to start high school having shared the screen with Marvel superheroes.

Keep ReadingShow less
Village officials expect new Water Department building by summer’s end

Caroline Farr-Killmer has been leading the effort to rebuild Millerton’s fire-ravaged Water Department building since last February.

Photo by Aly Morrissey

MILLERTON — Village officials expect a rebuild of the fire-ravaged Water Department building to begin soon, with the aim of completing it before the end of summer.

Fire project manager Caroline Farr-Killmer has been managing the effort to demolish and rebuild the village’s Public Works Department building since a fire destroyed it and all the equipment inside last winter. She said that Dutchess County Department of Health approval is the last hurdle for a new Water Department building before construction can start.

Keep ReadingShow less
Thai tea shop venture delayed over septic approvals

Kanchisar Jiradhanaiphat, left, and John Schildbach plan to open Muanjai Tea on Main Street in Millerton in early July.

Photo by Nathan Miller

MILLERTON — The opening of a proposed Thai tea shop on Main Street has been delayed while owners await approval from the Dutchess County Department of Health.

John Schildbach, who plans to open the shop with his wife, Kanchisar Jiradhanaiphat, in the former Candy-O’s space, said plans to include seating have complicated the approval process because of the building’s existing septic system.

Keep ReadingShow less
google preferred source

Want more of our stories on Google? Click here to make us a Preferred Source.

New owners pledge to keep original mission of Babette’s Kitchen

Jennifer Burgen, right, and Michael Burgen now own Babette’s Kitchen on Franklin Avenue in Millbrook. The duo have worked at the shop since 2024.

Photo Provided

MILLBROOK — A local eatery that has operated on Millbrook’s Franklin Avenue for more than 20 years is changing ownership.

The new owners at Babette’s Kitchen are two longtime employees. Jennifer Burgen, who has worked at Babette’s for the last three years, and Michael Burgen, who joined the kitchen in December 2024, took over earlier this month. Michael had previously been a general manager at Fern in Lakeville.

Keep ReadingShow less

Anita L. Gochey

Anita L. Gochey

CANAAN — Anita L. (King) Gochey, 85, of 77 South Canaan Rd. died June 5, 2026, at Geer Village. She was the wife of the late Lester Gochey. Anita was born July 16, 1940,in Winsted, daughter of the late Ivan and Irene (Dulude) King.

Anita was well known throughout the Northwest Corner. She worked for many local businesses and organizations. Anita worked at the Rexall Drug Store, C.A. Lindell and Sons, Bob’s Clothing, Brooks Pharmacy, and the Housatonic Valley Regional High School in the cafeteria.She used her skills in calligraphy to complete the record books for the North Canaan Congregational Church.Anita’s daughter remembers her as being very creative with cardboard, and a loving mom.

Keep ReadingShow less
NECC pilot program places a renewed emphasis on community-building

Carol Kneeland, left, Cyndhia Valle, center, and Irene Banning knit together on North East Community Center’s back porch during the first “Community Porch Party” on Wednesday, June 3.

Photo By Nathan Miller

MILLERTON — A new pilot program at the North East Community Center aims to bring in community members for chill hangs at the nonprofit’s office on South Center Street this summer.

The weekly “Community Porch Party” is an evolution of senior administrative assistant Ash Baldwin’s “Craft Collective,” which invited community members to enjoy a group crafting session where participants were encouraged to bring individual projects, swap tips and be together. The gathering on Wednesday, June 3, and the preceding “Craft Collective” meetings are part of a broader effort to provide accessible, community-building programming.

Keep ReadingShow less
google preferred source

Want more of our stories on Google? Click here to make us a Preferred Source.

google preferred source

Want more of our stories on Google? Click here to make us a Preferred Source.