MILLERTON — A wastewater system is one step closer to fruition after the North East Town Board approved the formation of a special district on Thursday, Nov. 12, a key procedural step that sets the stage for advancing the project.
Thursday’s unanimous vote to form the district came after a years-long wait for approval from the State Comptroller’s office, a necessary part of the formation of special municipal districts. Board members originally sent the petition to the comptroller’s office in May 2023 and received final approval in July 2026.
Building a municipal sewer takes patience and perseverance, Town Supervisor Chris Kennan said, drawing attention to the procedural hurdles and long timelines that can be impassable for some municipalities.
“The bureaucratic hurdles to get a wastewater system are daunting,” Kennan said. “But this is an important step.”
Kennan said the next step would be inviting the engineering firm designing the project, Tighe & Bond, to present an update to the board. He said he hoped construction could begin as soon as 2027, but that depends on shoring up the funding plan and the Village of Millerton’s not-yet-started search for construction bids.
“The village is the lead agency, they’re the ones taking most of the responsibility,” Kennan said. He added that requesting an appearance from Tighe & Bond representatives at an upcoming meeting could provide insights into the remaining hurdles and a tentative timeline.
Calls for a wastewater system in Millerton date to World War II. The current effort came to fruition in September 2023 when Rhinebeck-based engineering firm Tighe & Bond completed preliminary engineering and design work for the system. Village and town officials have spent the last three years securing funding and arriving at a final design for the system, culminating in March when Millerton secured a $3.5 million Congressionally Directed Spending grant that bridged the final gap.
The $13.8 million wastewater system will serve the core of the Village of Millerton and a commercial stretch of the Town of North East along U.S. Route 44. Under the proposed system, most properties would retain their existing septic tanks if they are code-compliant and in good working condition. The existing tanks will still be used to collect solid waste, but liquid waste will travel through the municipal system to a treatment center. Treated wastewater will then be directed to Webatuck Creek.
Kennan closed out discussion on the wastewater system with another note about persistence.
“It’s a very difficult process, which is one of the reasons why it’s so few towns are able to do this,” Kennan said. “I think when this gets done, and it will get done, it’s going to be seen as a great achievement.”







Millbrook celebrated Veterans Day with a color guard, a performance of “Taps,” and speeches from service members in honor of local war hero Charles Johnson.Photo by Graham Corrigan
Photo by Nathan Miller